Get Building Plans Approved

Procedure

There are two options for sanction of Building Plans of residential plots upto 500 sq. yards:

  • Self-certification by Architects empanelled by PDA
  • Sanction by PDA

SELF CERTIFICATION BY EMPANELLED ARCHITECTS

  • Application Form
  • Submission of building plans (In duplicate for plots upto 300 sq yards and in triplicate for plots more than 300 sq yards and upto 500 sq yards) one week prior to start of construction.
  • Security & Scrutiny fee in the form of a Demand Draft favouring ‘Estate Officer, Patiala Development Authority’ payable at Patiala.
  • Declaration

SANCTION BY PDA
In case the citizen does not want to exercise the option of self certification or in case the sanction of building plan is sought for any building other than a residential plot upto 500 sq. yards, the
following would be the procedure:

  • Application Form
  • Complete set of drawings duly cloth mounted with signatures of any Architect registered with Council of Architecture and the owner(s).
  • Security & Scrutiny fee in the form of a Demand Draft favouring ‘Estate Officer, Patiala Development Authority’ payable at Patiala.
  • In case application is being made by a person other than the owner, a self certified copy of the General Power of Attorney should be attached.

Time Limit: For Residential Plots – 30 working days
For Commercial Plots – 60 working days

NOTE: It would be preferred to print on A4 sheet.